September 2012

  • The works for the construction of temporary retaining piles in the TBM access shaft are in progress;
  • The archaeological survey in KORYDALLOS Station area is at an advanced stage;
  • The worksite installation of the Contractor in MANIATIKA Station area has been completed;
  • The works for the relocation of the kiosks located within the construction boundaries of DIMOTIKO THEATRO Station will commence soon.