  • Dimokratias Crossover: The works for the installation of struts at the final level are in progress.
  • DIMOKRATIAS Station: Completion of excavation works at level -2 of the station. In progress is the construction of slab -2. Moreover, in progress is the archaeological excavation of the northern access, the northern ventilation shaft and the emergency exit.
  • SINTRIVANI Station – REPORT: The Station excavation works were completed. In progress is the construction of foundation micropiles and the excavation of the northern access.
  • PAPAFI Station: The works for the excavation and the construction of foundation micropiles were completed. In progress are the works for the construction of the invert slab.
  • VOULGARI Station: The works for the construction of retaining micropiles were completed. In progress are the works for the construction of diaphragm walls and PUO network diversions.
  • NEA ELVETIA Station & Crossover: The works for the construction of temporary retaining anchors are in progress.
  • DEPOT: At the building complex I, is progress are the works for the construction of the roof slab at the ground floor and the installation of propping at the 1st floor, as well as the construction of the metal part of the building. At building complex II, in progress is the construction of the OCC bearing structure at buildings 2 and 9. Moreover, in progress is the construction of retaining walls and pile cladding walls, as well as the archaeological excavation in the surrounding area.
  • Cut and Cover Tunnel: The construction of the retaining piles and the cap beams of the tunnel is in progress. Moreover, excavation works and works for the installation of struts are under execution.