February 2016

  • Dimokratias Crossover: The works for the construction of level -2 were completed, while the preparation for the excavation of level -3 is in progress.
  • DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress.
  • SINTRIVANI Station: Preparatory works for the excavation of level -4 are in progress.
  • PANEPISTIMIO Station: Civil Works were completed.
  • PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls and for the construction of piles at the eastern access are in progress.
  • DEPOT: At the building complex II, the works for the construction of building 9 and the foundation of the Operations Control Centre (OCC) continue.
  • In progress is the TBM installation at NEA ELVETIA Station for the construction of the remaining Nea Elvetia – Analipsi tunnel section. Moreover, in progress is the construction of retaining piles at the C/C tunnel.