September 2014

  • NEW RAILWAY Station: The works for the restoration of openings (level 1) at the crossover were completed;
  • DIMOKRATIAS Station: The works for the traffic phase modification were completed;
  • AGHIA SOFIA Station: The archaeological excavation (Phase A’) at the southern part of the Station was completed;
  • SINTRIVANI Station: The works for the construction of piles at the southern ventilation shaft were completed, while the works for the construction of the NW shaft, as well as the archaeological excavation at the northern access are at an advanced stage;
  • PANEPISTIMIO Station: The excavation of level 4 is at an advanced stage;
  • PAPAFI Station: The works for the construction of the southern access are in progress;
  • EFKLIDIS Station: The works for the construction of the platform have commenced, while the works for the installation of the escalators are in progress;
  • ANALIPSI Station & Crossover: The works for the traffic phase modification have been completed;
  • PATRIKIOU Station & Crossover: The works for the construction of the sewage pipe shaft, as well as the excavation of the Station, are in progress;
  • VOULGARI Station: The works for PUO network diversions are in progress;
  • NEA ELVETIA Station & Crossover: The works for the construction of the foundation slab at the crossover are at an advanced stage;
  • DEPOT: The works for the excavation and retaining of building II-OCC, as well as the works for the construction of the ground floor slab at the train passing through area are at an advanced stage;
  • NEA ELVETIA Crossover: The works for the transfer of the two TBMs have been completed.