  • The assembly of the first Tunnel Boring Machine is at a completion phase.
  • The construction of diaphragm walls at Syntrivani will be completed soon (currently completed at a percentage of 86%).
  • In the area where the orphanage “Alexander the Great” was located, excavation works commenced for the construction of a building at the expense of AM where the 1st Laboratory of Special Professional Training in Thessaloniki will be housed.
  • Works related to the reinstatement of “Phoenix” Baths, which serves as the area where the archaeological finds of the 9th Byzantine Antiquities Department are stored, preserved and safeguarded, were completed.