January 2016

  • NOMARCHIA Station: The excavation of the station’s level -1 is completed, while the works for the installation of metal struts at level -1 are in progress.
  • NOMARCHIA Crossover: The excavation of the crossover’s level -1 is completed, while the works for the installation of metal struts at level -1 are in progress.
  • KALAMARIA Station: Works for the construction of perimeter piles and the pile cap beam at the northern section, as well as the works for the construction of struts made of reinforced concrete are in progress. Preparatory works for traffic arrangements – Phase D – and the construction of the road surface slab and the safety barriers for the by-pass of Pontou street are in progress.
  • ARETSOU Station: Works for construction of perimeter piles and pile cap beam intended for temporary retaining are in progress.
  • NEA KRINI Station: Works for the construction of the slab at level -1 and anchors at TBM tunnels’ fronts are in progress.
  • MIKRA Forestation: Works for the construction of the piles for the temporary retaining piles of the staircase are in progress.
  • MIKRA 2nd Crossover: Works for the construction of perimeter retaining piles are completed, while the construction of and perimeter piles’ cap beams is in progress.
  • MIKRA Forestation: Works for the construction of perimeter retaining piles, as well as the configuration of the worksite area are in progress; general excavation works are also in progress.
  • Kritis shaft: The construction of the 2nd level metal struts is completed.
  • Pontou shaft: The construction of perimeter piles and perimeter piles cap beam has been completed.
  • The preparation and approval of designs are in progress.
  • The expropriation of areas in ARETSOU, MIKRA (part) Stations and MIKRA Forestation has been completed, while the supplementary expropriation of an area in a small part of MIKRA Station is still pending.