Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

March 2014

  • Traffic arrangements (Phase B’) were implemented in district A’ of Piraeus Municipality (Piraiki area), while the reinstatement of traffic islands, stripings etc. is in progress;
  • The delimitation of individual worksite areas is in progress, while the following works are about to commence, namely the configuration of Lambraki Ave. U-turn, of sidewalks at Lambraki Ave. and of the area where Karaiskaki Tramway stop shall be constructed;
  • The works for the relocation of trolley-bus lines (lines 16 and 17) are at the completion phase, while the works for the relocation of trolley-bus line 20 and of all trolley-bus lines outside the Piraeus Tramway extension path are scheduled to commence immediately;
  • Works have been completed at Elliniko Tramway Depot building installations, the E/M installations are at the testing phase in building 2, while the works for the re-arrangement of building 1 room areas are in progress;
  • In the children playground area at Rizarios – Palaio Faliro, the WC buildings, the construction of the landplot fencing and the configuration of the surrounding area are at the completion phase.
WCAG