- At Ethnarhou Makariou street, the relocation of the storm water pipe in the section from Karaoli & Dimitriou street to Myrtidiotissis street has been completed, while in progress are the Tramway earthworks in the same area.
- At Mikras Asias street, the works for the construction of the Tramway from Papandreou Bridge to the beginning of Gr. Lambraki street (after the U-turn), outside the pocket area, have been completed. In progress are works for the construction of the Tramway at Papandreou bridge, where trackworks have already been completed.
- At Grigoriou Lambraki street, the works have been completed concerning the relocation of PUO networks, the urban planning works at the sidewalk across the street, as well as the works related to the Tramway and the urban planning at the adjacent sidewalk (including Lambraki and Evaggelistrias stops), at the section extending between the U-turn of Lambraki street and Venizelou street. In progress are the works for the construction of Deligianni stop.
- At Vas. Georgiou street, temporary traffic arrangements have been implemented on the part of the street from Iroon Polytechniou to Ethnikis Antistaseos streets. In progress is the archaeological excavation at the Substation construction location.
- At Ethnikis Antistaseos street, the PUO relocation works, as well as the works for the construction of the Tramway in the section from Ippodamias to Tsamadou streets, have been completed. In progress is the construction of the Tramway in that area.
(The location of the tramway corridor is the point of reference for the terms sidewalks “across the street” and “adjacent”).