• Dimokratias Crossover: Works for the construction of the foundation slab at the northern part have been completed.
• SINTRIVANI Crossover: Works for the concreting of provisional openings are in progress.
• PANEPISTIMIO Station: Works for the construction of masonry walls at level -1 have commenced.
• PAPAFI Station: Works for the construction of the roof slab are in progress.
• ANALIPSI Station and Crossover: Preparation works have been completed for the TBM2 arrival at the crossover, while in progress are works for the implementation of the next traffic phase.
• PATRIKIOU Station and Crossover: The construction of the roof slab at the Crossover, as well as the excavation at level -1 of the station have been completed, while in progress is the construction of the level -1 slab of the station.
• VOULGARI Station: Excavation works at level -1 have been completed, while the construction of the level -1 slab is in progress.
• TBM Tunnels: Works for the boring of the twin tunnels from NEA ELVETIA Station to PATRIKIOU Station have been completed. Works for the boring of TBM2 tunnel extending from PATRIKIOU Station to ANALIPSI Station are in progress.
• Cut and Cover Tunnel – Section I: In progress are works for the construction of the tunnel invert.