• New Railway Station: In progress are the works for the repair of the surface of the diaphragm walls.
• Dimokratias Crossing: Works for the repair of the diaphragm walls surface are in progress.
• DIMOKRATIAS Station: In progress are the works for the excavation of the pumping station and the installation of struts at the northern shaft.
• SINTRIVANI Station – EXPO: In progress are works for the construction of the emergency exit and the platform staircases, the repair of the diaphragm walls surface and the works for the excavation and temporary retaining of the southern ventilation shaft.
• PANEPISTIMIO Station: In progress are works for the repair of the diaphragm walls surface.
• PAPAFI Station: In progress are works for the excavation of the western emergency exit and the preparatory works for the implementation of the next traffic arrangement.
• EFKLEIDIS Station: In progress is the construction of the masonry walls at level -1 and plastering works at level -3.
• FLEMING Station: The construction of the platform has been completed, traffic phase D’ has been implemented and in progress is the construction of piles for the temporary retaining of the western access.
• ANALIPSI Station and Crossover: Works for the implementation of the next traffic phase have been completed.
• PATRIKIOU Station and Crossing: The construction of the retaining piles of the shafts has been completed, while at the completion stage is the construction of the level -1 slab of the station.
• VOULGARI Station: Excavation works for level -2 are in progress.
• NEA ELVETIA Station and Crossover: In progress is the construction of the foundation slab of the Station.
• Depot: In progress is the construction of the foundation slab of the washing plant. At Building Complex I, in progress are preparatory painting works at levels -3 and -2. At Building Complex II, in progress is the construction of the bearing structure of section V, I as well as of the slab at level -1. In progress is also the construction of pile lining works at the southern section, while the archaeological works have been completed in the Depot access area.
• TBM Tunnels: Works for the boring of TBM2 tunnel extending from PATRIKIOU Station to ANALIPSI Station have been completed. In progress is the construction of the TBM1 tunnel within PATRIKIOU Station, at the direction to ANALIPSI Station.
• Cut and Cover Tunnel – Section I: In progress are works for the construction of walls, supporting columns and waterproofing. Section III: In progress are works for the implementation of the next traffic phase.